Massachusetts lien waiver software for general contractors
Massachusetts-compliant forms in 2 minutes. Verbatim ch. 254 §32 templates. No PDF attachments, no chasing.
Massachusetts General Laws Chapter 254, §32
30-day free trial. No credit card. No demo call.
Why generic templates fail in Massachusetts
M.G.L. c. 254, §32 prescribes the Partial Waiver and Subordination of Lien and requires the form to follow the statutory text with no material deviation. That's a stricter standard than most states. A custom template is void.
The §32 form is more than a release. It carries a ten-line itemized payment table, a lender subordination that runs through the 25th day after the payment period, and a signature under the penalties of perjury. Generic templates carry none of that.
The forms we ship for Massachusetts
One statutory form, shipped exactly as the state code prescribes.
Partial waiver and subordination of lien§32
Release lien rights through the payment period and subordinate the remaining lien to the lender. One statutory form covers progress and final payments.
Massachusetts-specific features
The §32 form ships with the full statutory payment table (original contract amount, change orders, retainage, disputed claims) and the LENDER/MORTGAGEE header. Signed under the penalties of perjury, exactly as the statute prescribes.
Massachusetts lien waiver FAQ
Are non-statutory Massachusetts lien waivers enforceable?
Not when a notice of contract is on file. M.G.L. c. 254, §32 prescribes the Partial Waiver and Subordination of Lien and tolerates no material deviation. A waiver that strays from the statutory text is void.
Does Massachusetts require notarization for lien waivers?
No. The §32 form is signed under the penalties of perjury instead. That perjury clause is part of the prescribed text, so it can't be dropped.
What does the subordination in the §32 form do?
It subordinates the claimant's remaining lien to the lender's security interest for change orders, disputed claims, and further work through the 25th day after the end of the payment period, up to the amount the lender actually advances.
Is there a separate Massachusetts final waiver form?
No. §32 prescribes one form. The same partial waiver covers progress and final payments; the payment-period through-date carries whatever date you set.
Send a Massachusetts waiver in two minutes.
Massachusetts General Laws Chapter 254, §32 compliant. Signed PDF in your dashboard the moment your sub clicks submit.