First 5 customers: 6 months free.5 spots still open.
Claim your spotSouth Dakota lien waiver requirements
South Dakota lets you waive liens by joint check, with a written side agreement.
S.D. Codified Laws Chapter 44-9
The short version
South Dakota mechanic's and materialmen's liens sit in SDCL Chapter 44-9. The statute does not require a specific waiver form. It does carve out a joint-check waiver path: a supplier can waive lien rights by endorsing a joint check that references a separate written waiver agreement. That mechanism is unusual and worth knowing if you're paying suppliers through your subs.
At a glance
- SDCL Chapter 44-9 governs mechanic's and materialmen's liens
- No statutory waiver form is mandated
- Joint-check waivers require a conspicuous notice on the check
- Six-year limitation to enforce a recorded lien (§44-9-24)
South Dakota's joint-check waiver mechanism
Under the joint-check rule, a supplier furnishing materials to a contractor or subcontractor can waive lien rights by endorsing a joint check made out to both parties. The reverse of the check must carry a conspicuous notice referencing a separate written waiver agreement.
That notice must mention that the payees waive all claims under Title 5 and Title 44 to the extent of and as of the date of the check. It's a real waiver, but only if both the check and the side agreement are in place. Skip either piece and the waiver collapses.
Standard waiver practice for everything else
Outside the joint-check rule, South Dakota law does not specify what a waiver must say. That leaves it to general contract principles. Your form should name the amount, the project, the through-date, and the lien rights being released.
Use the four-document structure: conditional progress, unconditional progress, conditional final, unconditional final. Tie each one to a cleared payment. The statute won't carry you, so the paper has to.
The six-year limit on enforcing a recorded lien
SDCL §44-9-24 gives a claimant six years from recording to enforce the lien in court. After that, the lien is automatically cancelled. That's a longer tail than most states.
It matters because a sub holding a recorded but unenforced lien can sit on it for years. A clean unconditional waiver in your file, dated and signed after payment cleared, is the document that closes the door long before the six-year clock runs out.
Questions
Does South Dakota require a statutory lien waiver form?
No. SDCL Chapter 44-9 does not prescribe a waiver form.
How does the South Dakota joint-check waiver work?
A supplier waives lien rights by endorsing a joint check that conspicuously references a separate written waiver agreement.
How long can a recorded South Dakota lien sit before it expires?
Six years from recording, under SDCL §44-9-24.
Send a South Dakota waiver in two minutes.
The right form, the right notice, signed on a phone. Released when the check clears.
Get started