First 5 customers: 6 months free.5 spots still open.
Claim your spotNorth Carolina lien waiver requirements
North Carolina doesn't prescribe a form, but N.C.G.S. §22B-5 voids broad-form interim waivers.
North Carolina General Statutes Chapter 44A, Article 2; N.C.G.S. §22B-5
The short version
North Carolina does not require a statutory lien waiver form. The NCLTA publishes industry forms that most title underwriters accept, but those aren't required. The bigger rule is N.C.G.S. §22B-5: any contract clause that requires a sub to sign a broad-form waiver as a condition of a progress payment is void unless the waiver is limited to the specific payment received. Pre-contract waivers of future lien rights are also unenforceable.
At a glance
- N.C.G.S. Chapter 44A, Article 2: mechanic's lien framework
- N.C.G.S. §22B-5: voids broad-form interim waivers
- NCLTA industry forms accepted but not statutory
- 120-day deadline to file the lien from last furnishing
What North Carolina law actually requires
Chapter 44A, Article 2 sets the framework for North Carolina liens but does not publish a waiver form. The NCLTA forms (updated in 2014) are the de facto industry standard and are accepted by most title underwriters. They're not required by statute.
What is required: any waiver tied to a progress payment must be limited to the actual payment received. N.C.G.S. §22B-5 voids any contract clause that demands a broader release as a condition of the payment.
Pre-contract waivers don't work in North Carolina
An agreement to waive lien rights in anticipation of a contract is against public policy under Chapter 44A. You can't bake a lien waiver into the sub contract as a condition of award.
The lawful path is the same one every other non-statutory state takes: a per-payment waiver tied to a specific dollar amount, signed after the work has been performed. Broad-form, blanket, or prospective language gets read against you.
Common North Carolina mistakes
Putting a blanket lien waiver clause in the sub contract. §22B-5 voids it on interim payments and Chapter 44A voids it on pre-contract waivers.
Using a waiver that releases more than the amount of the payment. Title companies and courts will read those narrowly.
Missing the 120-day filing deadline. The clock runs from last furnishing, not from invoice or notice.
Questions
Does North Carolina require a statutory lien waiver form?
No. Chapter 44A does not prescribe a form. The NCLTA industry forms are widely used but not required.
Can a North Carolina sub waive lien rights in advance?
No. Pre-contract waivers of lien rights are against public policy under Chapter 44A, and §22B-5 voids broad-form interim waivers that exceed the amount of the progress payment received.
What is the deadline to file a North Carolina mechanic's lien?
120 days from the claimant's last day of furnishing labor or materials. The deadline applies the same way to contractors, subcontractors, and suppliers.
Send a North Carolina waiver in two minutes.
The right form, the right notice, signed on a phone. Released when the check clears.
Get started