Skip to main content
North Carolina (NC)

North Carolina lien waiver requirements

North Carolina doesn't prescribe a form, but N.C.G.S. §22B-5 voids broad-form interim waivers.

North Carolina General Statutes Chapter 44A, Article 2; N.C.G.S. §22B-5

The short version

North Carolina does not require a statutory lien waiver form. The NCLTA publishes industry forms that most title underwriters accept, but those aren't required. The bigger rule is N.C.G.S. §22B-5: any contract clause that requires a sub to sign a broad-form waiver as a condition of a progress payment is void unless the waiver is limited to the specific payment received. Pre-contract waivers of future lien rights are also unenforceable.

At a glance

  • N.C.G.S. Chapter 44A, Article 2: mechanic's lien framework
  • N.C.G.S. §22B-5: voids broad-form interim waivers
  • NCLTA industry forms accepted but not statutory
  • 120-day deadline to file the lien from last furnishing

What North Carolina law actually requires

Chapter 44A, Article 2 sets the framework for North Carolina liens but does not publish a waiver form. The NCLTA forms (updated in 2014) are the de facto industry standard and are accepted by most title underwriters. They're not required by statute.

What is required: any waiver tied to a progress payment must be limited to the actual payment received. N.C.G.S. §22B-5 voids any contract clause that demands a broader release as a condition of the payment.

Pre-contract waivers don't work in North Carolina

An agreement to waive lien rights in anticipation of a contract is against public policy under Chapter 44A. You can't bake a lien waiver into the sub contract as a condition of award.

The lawful path is the same one every other non-statutory state takes: a per-payment waiver tied to a specific dollar amount, signed after the work has been performed. Broad-form, blanket, or prospective language gets read against you.

Common North Carolina mistakes

Putting a blanket lien waiver clause in the sub contract. §22B-5 voids it on interim payments and Chapter 44A voids it on pre-contract waivers.

Using a waiver that releases more than the amount of the payment. Title companies and courts will read those narrowly.

Missing the 120-day filing deadline. The clock runs from last furnishing, not from invoice or notice.

Questions

Does North Carolina require a statutory lien waiver form?

No. Chapter 44A does not prescribe a form. The NCLTA industry forms are widely used but not required.

Can a North Carolina sub waive lien rights in advance?

No. Pre-contract waivers of lien rights are against public policy under Chapter 44A, and §22B-5 voids broad-form interim waivers that exceed the amount of the progress payment received.

What is the deadline to file a North Carolina mechanic's lien?

120 days from the claimant's last day of furnishing labor or materials. The deadline applies the same way to contractors, subcontractors, and suppliers.

Free tool

Check the North Carolina lien filing deadline

Enter the last day of furnishing and get the North Carolina filing deadline to the day, with the notice rules that go with it.

Open the lien deadline calculator

Send a North Carolina waiver in two minutes.

The right form, the right notice, signed on a phone. Released when the check clears.

Get started